Justia Environmental Law Opinion Summaries

by
The Supreme Court affirmed the decision of the Brule County Board of Commissioners finding that Surat Farms LLC impermissibly altered an intermittent watercourse. Upon Albert Delany’s filing of a drainage complaint with Brule County, the Board found that Surat “altered the natural flow of the water” running from Delany’s land to Surat’s land and required Surat to restore the natural flow of water or otherwise ensure the drainage of the Delany property. The circuit court affirmed the Board’s decision in all respects. The Supreme Court affirmed, holding (1) the evidence supported the circuit court’s finding that Surat’s drain system improperly interfered with Delany’s drainage rights; and (2) the circuit court did not err in awarding injunctive relief. View "Surat Farms, LLC v. Brule County Board of Commissioners" on Justia Law

by
Landowners from the Buffalo area appealed a district court judgment affirming the Department of Health's decision to issue Rolling Green Family Farms an animal feeding operation (AFO) permit. The landowners argued the Department erred by issuing Rolling Green an AFO permit and by failing to reopen the public comment period after Rolling Green provided further information to supplement its permit application. Finding no reversible error, the North Dakota Supreme Court affirmed. View "Coon v. N.D. Dep't of Health" on Justia Law

by
Tennessee Gas applied to several federal and state agencies seeking approval to build the Orion interstate pipeline project, comprising 12.9 miles of pipeline looping that would transport 135,000 dekatherms of natural gas per day via Pennsylvania. Approximately 99.5% of the new pipeline would run alongside existing pipeline. The Pennsylvania Department of Environmental Protection issued a permit approving the project. Riverkeeper argued that the court lacked jurisdiction to rule on its challenge because PADEP’s order was not final and that PADEP made an erroneous “water dependency” finding and improperly rejected a “compression” alternative to the pipeline project. The Third Circuit concluded that PADEP’s decision was final and upheld the decision on the merits because the agency’s unique interpretation of water dependency was reasonable and worthy of deference. PADEP considered and rejected the compression alternative for reasons that are supported by the record. Where an interstate pipeline project is proposed to be constructed,15 U.S.C. 717f provides “original and exclusive jurisdiction over any civil action for the review of an order or action of a . . . State administrative agency acting pursuant to Federal law to issue . . . any permit, license, concurrence, or approval . . . required under Federal law,” View "Delaware Riverkeeper Network v. Secretary, Pennsylvania Department Environmental Protection" on Justia Law

by
The Ninth Circuit affirmed the district court's approval of a consent decree between the EPA and the Sierra Club that set a schedule for the EPA to promulgate designations whether geographic areas met national ambient air quality standards for sulfur dioxide under the Clean Air Act (CAA), 42 U.S.C. 7401. The panel rejected the States' objections to the consent decree, holding that as long as the EPA sticks to the schedule in the consent decree, the Sierra Club will not advance its lawsuit against the EPA. Therefore, the consent decree did not prohibit the EPA from promulgating designations prior to those deadlines, nor did it otherwise constrain the agency's discretion. The panel explained that, because the consent decree did not bind the States to do nor not to do anything, imposed no legal duties or obligations on them at all, and did not purport to resolve any claims they might have, the States could not block the consent decree by merely withholding their consent. View "North Dakota v. Pruitt" on Justia Law

by
The Ninth Circuit affirmed summary judgment for the FWS in an action challenging the FWS's determination that the Sonoran Desert Area bald eagle was not a distinct population segment eligible for listing under the Endangered Species Act (ESA), 16 U.S.C. 1533. The panel held that FWS reasonably concluded that, while the combination of unusual characteristics in a discrete population was sufficient to satisfy the persistence factor, those characteristics did not by themselves necessarily require a conclusion that the desert eagle population segment was ecologically or biologically significant for the bald eagle taxon as a whole; FWS reasonably concluded that if the desert eagle population segment were "extirpated," this would not create a significant gap in the range of the taxon; and FWS directly addressed climate change in its 2012 decision. View "Center for Biological Diversity v. Zinke" on Justia Law

by
In 2010, Omni, the landowner and developer, sought approval for construction of a shopping center on 11 acres of property zoned commercial, to consist of 10 retail buildings. Monterey County approved the project. An association of community members challenged the approval under the California Environmental Quality Act, Public Resources Code 21000 (CEQA). The trial court denied the petition as to the claimed CEQA violations but ordered an interlocutory remand to allow the county to clarify whether the project was consistent with the county’s general plan requirement that the project have a long-term, sustainable water supply. On remand, the Board of Supervisors clarified that the project “has a long-term sustainable water supply, both in quality and quantity to serve the development in accordance with the 2010 Monterey County General Plan Policies. The court entered judgment in favor of the county and Omni. The court of appeal affirmed, rejecting claims that the county violated the association’s right to procedural due process on interlocutory remand and violated CEQA because the water supply analysis was inadequate, the analysis of the project’s consistency with the general plan was inadequate, the environmental impact report’s traffic analysis was inadequate, and environmental review of Omni’s project was improperly segmented. View "Highway 68 Coalition v. County of Monterey" on Justia Law

by
About 99.5% of the Orion Project, 12.9 miles of pipeline looping that would transport an additional 135,000 dekatherms per day of natural gas through Pennsylvania, would run alongside existing pipelines. According to Riverkeeper, construction will lead to deforestation, destruction of wetland habitats, and other forms of environmental damage. Riverkeeper asserts that such damage can be avoided by building or upgrading a compressor station. The Army Corps of Engineers, which administers certain provisions of the Clean Water Act, 33 U.S.C. 1344(a), 1362(7) issued a Section 404 permit approving the project. The Third Circuit rejected Riverkeeper’s challenge. The Corps considered the compression alternative but rejected it for reasons supported by the record. While the compression alternative would disturb less land, its impact would be mostly permanent. The pipeline project would disturb more land, but its impact would be mostly temporary. In making a policy choice between those environmental tradeoffs, the agency’s discretion “was at its apex.” View "Delaware Riverkeeper Network v. United States Army Corps of Engineers" on Justia Law

by
Plaintiffs challenged the Government's approval of the location, construction, and specifications for a military base in Okinawa, Japan. Plaintiffs sought claims for declaratory and injunctive relief based on the Government's alleged violations of Section 402 of the National Historic Preservation Act (NHPA), 54 U.S.C. 307101(e), and the Administrative Procedure Act (APA), 5 U.S.C. 701 et seq. The Ninth Circuit held that plaintiffs have standing to bring declaratory relief claims limited to whether the Government's evaluation, information gathering, and consultation process discharged the Government's obligations under the NHPA and otherwise satisfied the requirements of the APA. The panel also held that plaintiffs' injunctive relief claim did not present a political question. Accordingly, the panel affirmed the district court's conclusion that plaintiffs' claims for declaratory and injunctive relief did not present a political question; reversed the district court's conclusion that plaintiffs lacked standing to seek declaratory relief; and reversed the district court's conclusion that plaintiffs' claim for injunctive relief presented a political question. The panel remanded for further proceedings. View "Center for Biological Diversity v. Mattis" on Justia Law

by
Constitution petitioned for review of the Department's decision denying its application for certification pursuant to Section 401 of the Federal Water Pollution Control Act, more commonly known as the Clean Water Act (CWA), 33 U.S.C. 1341. Constitution sought certification that its proposed interstate natural gas pipeline would comply with New York State water quality standards. NYSDEC denied the application on the ground that Constitution had not provided sufficient information. The Second Circuit held that, to the extent Constitution challenged the timeliness of the NYSDEC decision, the petition was dismissed for lack of jurisdiction. On the merits, the court held that NYSDEC's actions were within its statutory authority and that its decision was not arbitrary or capricious. The court deferred to NYSDEC's expertise as to the significance of the information requested from Constitution, given the record evidence supporting the relevance of that information to NYSDEC's certification determination. Accordingly, the court denied the petition for review. View "Constitution Pipeline Co. v. New York Sate Department of Environmental Conservation" on Justia Law

by
The Oak Ridge, Tennessee uranium-enrichment facilities for the Manhattan Project, the World War II effort to build the first atomic bomb, have been inactive since the mid-1980s. The Department of Energy has worked to clean up the hazardous waste and hired Bechtel, a global engineering and construction firm. Bechtel hired Eagle to help decontaminate the complex, which required the demolition of buildings and equipment across the 2,200-acre complex and removal of radioactive nuclear waste, followed by decontamination of the soil and groundwater to make the site safe for redevelopment. Eagle’s work proved significantly more challenging and expensive than either party anticipated. Their contract allowed Bechtel to make changes; if those changes caused Eagle’s costs to increase, Bechtel was to make equitable adjustments in price and time for performance. Eight years after completing its work, Eagle filed suit, seeking compensation for its extra work and for excess waste that Eagle removed. The district court awarded Eagle the full amount of each request, plus interest and attorney’s fees. The Sixth Circuit affirmed the award of damages and attorney’s fees, but remanded so that the court can recalculate the interest to which Eagle is entitled under the Tennessee Prompt Pay Act. View "Eagle Supply & Manufacturing L.P. v. Bechtel Jacobs Co." on Justia Law