Chlorine Institute, Inc. v. FRA, et al.

by
The Institute challenged the final rule promulgated by the FRA to implement section 104 of the Rail Safety Improvement Act of 2008, Pub. L. No. 110-432 section 104(a)(1), 122 Stat. 4848, 4857. Section 104 required a qualifying rail carrier to submit an implementation plan to install a "positive train control" (PTC) system no later than December 31, 2015 on certain tracks used for passenger service or for transporting "poison- or toxic- by-inhalation" hazardous material (PIH or TIH). The court concluded that the Institute's challenge was not ripe because it had not established that its members now faced a present or imminent injury from the 2012 Final Rule's omission of a two-part risk assessment test. Accordingly, the court dismissed the Institute's petition for lack of jurisdiction. View "Chlorine Institute, Inc. v. FRA, et al." on Justia Law